The main airport works program will be divided into three primary packages of work.
image

The first package will cover all Stage 1 earthworks, drainage and utilities, together with airside pavements. The Expression of Interest for the first package is planned for release to market in early February 2018. It is expected that a preferred tenderer will be contracted in the first quarter of 2019 and that works will commence early in the second half of 2019.

Western Sydney Airport is one of the largest civil engineering projects underway in Australia. Construction will commence in the second half of 2018 and the airport will open in 2026. The Stage 1 airport will have a single 3.7-kilometre runway and facilities to cater for up to 10 million annual passengers. It will be a full-service airport offering domestic, international and freight services.

WSA Co's procurement approach has been developed in line with its objectives, which are:

  • improving access to aviation services in Western Sydney;
  • resolving the long-term aviation capacity issue in the Sydney basin;
  • maximising the value of a Western Sydney Airport as a national asset;
  • optimising the benefit of Western Sydney Airport on employment and investment in Western Sydney; and
  • effectively integrating with new and existing initiatives in the Western Sydney area.

WSA Co's procurement approach includes:

  • assigning risks to parties that are best capable of managing the risks;
  • packaging the works to commence bulk earthworks as soon as practicable;
  • defining interfaces between the various works packages clearly;
  • undertaking Enabling Activities to facilitate the Main Airport Works packages;
  • ensuring the works are fully integrated prior to operational readiness testing providing opportunities for innovation and sustainable outcomes within each package and consistent with the Environmental Impact Statement and Airport Plan; and
  • mechanisms for achieving appropriate urban design, amenity outcomes, sustainability objectives and seamless integration with other transport modes.

The first package of the main airport works will involve the design and construction of the following work elements:

  • Site clearance.
  • Topsoil management.
  • Bulk earthworks in preparation for handover to other Main Airport Works packages.
  • Trunk and cross drainage.
  • Detention basins and water quality treatment facilities.
  • Provisioning for airside services and utilities, including potable water, recycled water, sewage, waste disposal, electricity supply, gas, communications and aviation services.
  • Pavements for the northern runway, taxiways and aprons.
  • Airside perimeter and emergency roads.
  • Airside grassing and fencing.
  • Temporary works including access arrangements for other works packages.

Further details on the upcoming WSA works will be presented at an industry information session on Tuesday December 5, 2017. Registration for the event is now open and qualified service providers are invited to attend.

The second major package will be the terminal building and associated airside and landside interface works.

The third package will cover the landside roads, carparks and associated works.

WSA Co intends to commence procurement of packages two and three after awarding the first package.

A number of smaller specialist packages for services such as IT, security and baggage handling systems will be issued for tender separately and integrate with the main works.

The successful tenderer/s will need to meet the environmental, safety, and security requirements under the Airport PlanEnvironmental Impact Statement and functional specifications.