Multiplex hits milestone on NEXTDC data centre

Multiplex has topped out the structure of NEXTDC’s S3 data centre in Artarmon on Sydney’s lower North Shore.

Multiplex has topped out the structure of NEXTDC’s S3 data centre in Artarmon on Sydney’s lower North Shore.

Designed by architects Greenbox, NEXTDC’s new S3 data centre comprises around 26,770 square metres of data halls and ancillary infrastructure over eight storeys, delivering more than 20,000 square metres of IT space.

The nine-storey building caters to a growing need for data storage, cloud and interconnection capability as digital transformation accelerates.

The S3 project has employed a total of 2042 workers to date.

“We are delighted to continue our on-going collaboration with NEXTDC, reaching this fantastic milestone on Sydney’s newest data centre following the successful delivery of S2 Sydney and P2 Perth,” David Ghannoum, Multiplex Regional Managing Director NSW said.

S3 Sydney is NEXTDC’s third and largest data centre in Sydney and directly interconnects to the existing S1 and S2 Sydney data centres and into NEXTDC’s broader national digital infrastructure platform.

It comprises a range of amenities for tenants including comfortable workspaces, collaboration zones, car parking and over 4000 square metres of critical office space.

“This is an important milestone as S3 is a crucial digital infrastructure asset for NSW,” Simon Cooper, NEXTDC Chief Operating Officer said.

“We couldn’t be happier with construction progress to date, despite the adverse health and weather conditions which our project team has navigated safely and effectively.

“As our largest facility to date, and the first of our third-generation data centres, S3 is on track to deliver critical digital capability and further strengthen cloud access in the region, on time.”

The structure is predominantly a ‘hybrid’ scheme using a combination of reinforced and post tensioned concrete and structural steel K frame for lateral bracing, in lieu of the more conventional concrete shear walls.

Environmentally sustainable design features will be incorporated into the building’s design, including a reduced energy consumption cooling system, ‘free cooling’ to further reduce power consumption and optimised efficiency levels.

Construction of Stage 1 of NEXTDC’s S3 data centre is on track for completion in H2 2022.